Casa Aguila will arguably be the most advanced home ever built in San Diego County, looking to achieve many firsts for our region. It will be San Diego's first Certified Passive House, seek the County's first onsite wastewater treatment permit, seek the County's first permit to utilize all collected rainwater for all indoor water use, and strive for eventual grid-disconnection through utilization of battery power, Solar PV, and a 45-foot wind turbine (the blades alone are 17 feet tall!).

The project is located in Ramona, CA and is named for the Golden Eagles which frequently fly over the property.

Wednesday, August 12, 2015

Dual-Axis Solar Tracker Installation

Today we craned in 3 dual-axis DEGER D-60 solar trackers, which will each hold 24 panels to create a 21.6 kW PV system. These trackers are huge - they measure about 27 feet across and 17 feet deep! They rotate on a dual-axis so they can detect the maximum point of light irradiance every day.



This chart shows the difference in yield from a dual-axis DEGER tracker vs. a standard fixed system (such as roof panel PV system) that doesn't follow the sun. 




Monday, August 10, 2015

August updates - Landscaping and solar preparation

Southern Elevation, "Screened Porch" off the main living area
Cluster of drought tolerant sago palms
Casa Aguila as of August 7th, 2015
Final Color Coat of Stucco recently applied
Another look at the poured-in-place concrete wall
Triple-glazed Unilux windows - very fire-resistant and low heat transfer
Hemlock paneled ceiling in the Master Suite
Bases established for the three dual-axis Deger solar trackers

Tuesday, June 30, 2015

Water tower and wind turbine prep

Scratch Coat of Stucco has been applied.
Excavation for the footing of the UGE VisionAir5 Wind Turbine
Pads established on the hill, above the house, for two of the 8 x 10,000 gallon Water Tanks 

Friday, June 12, 2015

Timelapse updates - Interior and Exterior

Here's a timelapse of the exterior of the project from April. Unilux doors and windows installed!



And here's one of the interior work in May... someone accidentally blocked the camera with a board for a couple weeks, but what can you expect on a construction site! We'll work out the timelapse kinks for next time.

Wednesday, June 3, 2015

June photo update

We've covered all that black Prosoco - here's what the project looks like currently!



Tuesday, May 26, 2015

Onsite Wastewater Treatment System: Work Commences!


Jeff checking out the new surge tank

AGB Team Member and Water Expert Extraordinaire, Bill Wilson, at work in the old septic tank

Site area for the Food Forest that will be irrigated by all the treated wastewater

Wednesday, May 20, 2015

This is what the BioPCM looks like installed

Installing the BioPCM insulation was simple, we stapled the sheets to the studs along the ceiling and walls. You can feel the difference in temperature when you walk into the room.